Filters
Question type

Study Flashcards

In the probabilistic approach to precedence network analysis,the duration estimate that is given the highest weighting in calculating the expected duration for an activity is:


A) duration of the immediately prior activity.
B) duration of the immediately following activity.
C) most likely duration.
D) optimistic duration.
E) pessimistic duration.

F) B) and D)
G) B) and E)

Correct Answer

verifed

verified

Projects involve routine operations that are performed repeatedly.

A) True
B) False

Correct Answer

verifed

verified

The critical path has zero path slack time.

A) True
B) False

Correct Answer

verifed

verified

Which of the following is not part of the project management triangle?


A) risk
B) cost
C) schedule
D) scope

E) B) and C)
F) A) and D)

Correct Answer

verifed

verified

A hierarchical listing of what must be done during a project is called a project matrix.

A) True
B) False

Correct Answer

verifed

verified

Activity slack is the difference between the latest finish and earliest finish times.

A) True
B) False

Correct Answer

verifed

verified

A project manager for Durable Construction Co.is about to build a house involving the following six activities: A project manager for Durable Construction Co.is about to build a house involving the following six activities:   What is the estimated slack time for the path B-D-F? A) 0 days B) 30 days C) 40 days D) 50 days E) 100 days What is the estimated slack time for the path B-D-F?


A) 0 days
B) 30 days
C) 40 days
D) 50 days
E) 100 days

F) B) and E)
G) A) and B)

Correct Answer

verifed

verified

A project manager for Durable Construction Co.is about to build a house involving the following six activities: A project manager for Durable Construction Co.is about to build a house involving the following six activities:   What is the estimated expected (mean) duration for project completion? A) 160 days B) 170 days C) 200 days D) 210 days E) 300 days What is the estimated expected (mean) duration for project completion?


A) 160 days
B) 170 days
C) 200 days
D) 210 days
E) 300 days

F) C) and D)
G) B) and E)

Correct Answer

verifed

verified

The owner of Ace Building Co.is about to begin work on a project comprised of the following four activities: The owner of Ace Building Co.is about to begin work on a project comprised of the following four activities:   What is the estimated slack time for the path B-D? A) 0 days B) 19 days C) 20 days D) 79 days E) 80 days What is the estimated slack time for the path B-D?


A) 0 days
B) 19 days
C) 20 days
D) 79 days
E) 80 days

F) A) and B)
G) D) and E)

Correct Answer

verifed

verified

Simulation can be used for cases in which network activity durations are dependent.

A) True
B) False

Correct Answer

verifed

verified

The optimum project length in crashing occurs when the cumulative cost of crashing equals savings in the indirect costs.

A) True
B) False

Correct Answer

verifed

verified

The probability of occurrence of risk events is lower near the beginning of a project and higher near the end of the project.

A) True
B) False

Correct Answer

verifed

verified

The path in a PERT/CPM precedence network with the fewest activities and shortest duration is referred to as the critical path.

A) True
B) False

Correct Answer

verifed

verified

Uncontrolled growth in the number of activities that end up being included as a part of a project is called:


A) the critical path.
B) project slack.
C) scope creep.
D) indirect costs.
E) time-cost trade-offs.

F) B) and D)
G) B) and E)

Correct Answer

verifed

verified

A project manager for Durable Construction Co.is about to build a house involving the following six activities: A project manager for Durable Construction Co.is about to build a house involving the following six activities:   What is the estimated expected (mean) duration for activity E? A) 35 days B) 36 days C) 39 days D) 40 days E) 45 days What is the estimated expected (mean) duration for activity E?


A) 35 days
B) 36 days
C) 39 days
D) 40 days
E) 45 days

F) B) and C)
G) A) and E)

Correct Answer

verifed

verified

A project manager usually staffs the human resources required for a project by hiring outside specialists that only work for the company for the duration of the project.

A) True
B) False

Correct Answer

verifed

verified

In order to determine the probability of timely project completion,it is sometimes necessary to take into account paths other than the critical path.

A) True
B) False

Correct Answer

verifed

verified

The life cycle of a project does not include which of the following phases?


A) Initiation
B) Planning and scheduling
C) Growth and maturity
D) Closeout
E) Execution

F) A) and B)
G) C) and E)

Correct Answer

verifed

verified

What is the probability that the critical path for this project will be completed within 75 weeks? 80 weeks? 85 weeks? 90 weeks? 11eab92b_c478_6c59_99e6_3b8caf9e27de

Correct Answer

verifed

verified

.5; .8413;...

View Answer

The task of identifying risks should involve everyone associated with the project.

A) True
B) False

Correct Answer

verifed

verified

Showing 61 - 80 of 131

Related Exams

Show Answer