In the execution phase of a project's life cycle, activities are guided by decisions that were made in the __________ phase.


A) initiating
B) planning
C) monitoring/controlling
D) closing
E) assessment

F) D) and E)
G) All of the above

Correct Answer

verifed

verified

In order to determine the probability of timely project completion, it is sometimes necessary to take into account paths other than the critical path.

A) True
B) False

Correct Answer

verifed

verified

All of the following are areas of knowledge that a project manager should possess, except


A) managing integration.
B) managing procurement.
C) managing stakeholders.
D) managing scope.
E) managing operations.

F) B) and D)
G) All of the above

Correct Answer

verifed

verified

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated expected (mean) time for activity D? A) 32 days B) 41 days C) 44 days D) 42 days E) 40 days What is the estimated expected (mean) time for activity D?


A) 32 days
B) 41 days
C) 44 days
D) 42 days
E) 40 days

F) B) and D)
G) All of the above

Correct Answer

verifed

verified

E

If the expected length of a path is more than 2.5 standard deviations less than a desired project completion time, the path will not be a factor in assessing the probability of finishing the project on time.

A) True
B) False

Correct Answer

verifed

verified

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the probability that this project will be completed within 130 days? A) .8413 B) .90 C) .9544 D) .9772 E) .9987 What is the probability that this project will be completed within 130 days?


A) .8413
B) .90
C) .9544
D) .9772
E) .9987

F) All of the above
G) C) and E)

Correct Answer

verifed

verified

The latest starting time for an activity is equal to the latest finish time minus the activity time.

A) True
B) False

Correct Answer

verifed

verified

True

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated expected (mean) time for activity Y? A) 30 days B) 29 days C) 38 days D) 26 days E) 35 days What is the estimated expected (mean) time for activity Y?


A) 30 days
B) 29 days
C) 38 days
D) 26 days
E) 35 days

F) B) and C)
G) A) and D)

Correct Answer

verifed

verified

Activity 7-8 is directly preceded by two activities-activity 5-7 and activity 6-7. Activity 5-7 has an expected time of five and an ES time of six. Activity 6-7 has an expected time of seven and an ES time of seven. Activity 7-8 has an expected time of 10. The ES for activity 7-8 is


A) 11.
B) 14.
C) 21.
D) 24.
E) 25.

F) A) and E)
G) B) and E)

Correct Answer

verifed

verified

Which of the following is not one of the six key decisions in project management? (I) Selecting the project team(II) Deciding on the project manager's title(III) Managing and controlling project resources(IV) Deciding which projects to implement(V) Selecting the project manager


A) I
B) II
C) III
D) IV
E) V

F) B) and C)
G) C) and D)

Correct Answer

verifed

verified

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated standard deviation in the time for activity Z? A) 3 days B) 2 days C) 4 days D) 8 days E) 5 days What is the estimated standard deviation in the time for activity Z?


A) 3 days
B) 2 days
C) 4 days
D) 8 days
E) 5 days

F) None of the above
G) A) and D)

Correct Answer

verifed

verified

Which of the following are limitations of PERT and CPM?(I) Time estimates may include a fudge factor.(II) Important activities may be overlooked.(III) It is an after-the-fact analysis.


A) I and II
B) I, II, and III
C) I and III
D) II and III
E) I only

F) A) and B)
G) None of the above

Correct Answer

verifed

verified

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated expected (mean) time for activity E? A) 31 weeks B) 38 weeks C) 39 weeks D) 40 weeks E) 43 weeks What is the estimated expected (mean) time for activity E?


A) 31 weeks
B) 38 weeks
C) 39 weeks
D) 40 weeks
E) 43 weeks

F) A) and E)
G) B) and E)

Correct Answer

verifed

verified

Gantt charts are most closely associated with


A) JIT.
B) PERT.
C) MRP.
D) MRPII.
E) Six Sigma.

F) A) and B)
G) B) and E)

Correct Answer

verifed

verified

The path in a network with the average length of time to completion is called the critical path.

A) True
B) False

Correct Answer

verifed

verified

A project is represented by the following diagram: A project is represented by the following diagram:   The critical path for the network shown is: A) 1-3-6-7. B) 1-2-4-7. C) 1-4-7. D) 1-3-4-7. E) 1-2-5-7. The critical path for the network shown is:


A) 1-3-6-7.
B) 1-2-4-7.
C) 1-4-7.
D) 1-3-4-7.
E) 1-2-5-7.

F) All of the above
G) B) and C)

Correct Answer

verifed

verified

The total cost of crashing any one activity should never exceed 20 percent of the total cost of the original project.

A) True
B) False

Correct Answer

verifed

verified

Concerning PERT and CPM


A) These are two different names for essentially the same technique.
B) CPM tends to focus more on the critical path; PERT focuses on the parallel paths.
C) PERT gives a clearer indication of activity slack, while CPM gives a better picture of path slack.
D) Because of its recent discovery, much less is known about CPM than PERT.
E) CPM is useful for project manager selection; PERT is useful for project team selection.

F) A) and D)
G) C) and D)

Correct Answer

verifed

verified

At which point does crashing of a project cease?


A) when the project is completed
B) when no additional crashing is possible
C) when the cost to crash equals or exceeds the benefit of crashing
D) when the project is one-half completed
E) when the team has been disbanded

F) A) and B)
G) C) and E)

Correct Answer

verifed

verified

C

If two consecutive activities have shared slack, this means that each of them can use only half of the slack without delaying completion of the project.

A) True
B) False

Correct Answer

verifed

verified