The standard deviation of the critical path is equal to the sum of the standard deviations of all of the activities on the critical path.

A) True
B) False

Correct Answer

verifed

verified

Once a project is approved and underway, project managers are only responsible for effectively managing time and costs which, if done well, will assure project completion on time and on budget.

A) True
B) False

Correct Answer

verifed

verified

Path probabilities are calculated by dividing path mean by path standard deviations.

A) True
B) False

Correct Answer

verifed

verified

A hierarchical listing of what must be done in a project is called a


A) work breakdown structure (WBS) .
B) PERT.
C) planning matrix.
D) crashing plan.
E) critical path.

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated slack time for activity D? A) 0 days B) 19 days C) 20 days D) 79 days E) 80 days What is the estimated slack time for activity D?


A) 0 days
B) 19 days
C) 20 days
D) 79 days
E) 80 days

F) D) and E)
G) A) and B)

Correct Answer

verifed

verified

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated standard deviation in the time for activity D? A) 0 days B) 2 days C) 3 days D) 4 days E) 12 days What is the estimated standard deviation in the time for activity D?


A) 0 days
B) 2 days
C) 3 days
D) 4 days
E) 12 days

F) D) and E)
G) A) and E)

Correct Answer

verifed

verified

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated slack time for activity E? A) 0 weeks B) 3 weeks C) 9 weeks D) 11 weeks E) 12 weeks What is the estimated slack time for activity E?


A) 0 weeks
B) 3 weeks
C) 9 weeks
D) 11 weeks
E) 12 weeks

F) A) and E)
G) A) and B)

Correct Answer

verifed

verified

Activity 4-5 in a network diagram has an optimistic time estimate of five days, a most likely time estimate of seven days, and a pessimistic time estimate of 10 days. Its expected time (in days) is approximately


A) 5.
B) 6.
C) 7.
D) 8.
E) 9.

F) A) and E)
G) B) and C)

Correct Answer

verifed

verified

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated standard deviation in the time for activity E? A) 1 day B) 2 days C) 3 days D) 4 days E) 5 days What is the estimated standard deviation in the time for activity E?


A) 1 day
B) 2 days
C) 3 days
D) 4 days
E) 5 days

F) A) and C)
G) B) and E)

Correct Answer

verifed

verified

Once a project is underway, the project manager usually is not responsible for effectively managing


A) the people.
B) costs.
C) resources.
D) time.
E) project priority.

F) A) and C)
G) A) and B)

Correct Answer

verifed

verified

Matrix organizations transfer control of workers to project managers for the duration of the project.

A) True
B) False

Correct Answer

verifed

verified

Many activities have slack time; if we add these slack times together, this represents the potential improvement in early completion for the project.

A) True
B) False

Correct Answer

verifed

verified

In project network analysis, "slack" refers to the difference between


A) observed and predicted times.
B) optimistic and pessimistic times.
C) mean and modal times.
D) finish and start times.
E) latest and earliest times.

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

A sequence of activities that leads from the starting node to the finishing node is called a


A) path.
B) sequel.
C) trail.
D) critical sequence.
E) time line.

F) C) and D)
G) A) and C)

Correct Answer

verifed

verified

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated standard deviation in the time for activity E? A) 0 week B) 1 week C) 2 weeks D) 3 weeks E) 4 weeks What is the estimated standard deviation in the time for activity E?


A) 0 week
B) 1 week
C) 2 weeks
D) 3 weeks
E) 4 weeks

F) C) and D)
G) A) and B)

Correct Answer

verifed

verified

One upside to terminating a project that is not going as well as planned is that


A) poorly performing project team members will be kept from causing trouble elsewhere.
B) no additional costs will be incurred.
C) poor project managers will be weeded out.
D) resources can perhaps be put to better use elsewhere.
E) project completion will be hastened.

F) B) and E)
G) A) and B)

Correct Answer

verifed

verified

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the probability that the critical path for this project will be completed within 200 days? A) .8413 B) .9544 C) .9772 D) .9974 E) .9987 What is the probability that the critical path for this project will be completed within 200 days?


A) .8413
B) .9544
C) .9772
D) .9974
E) .9987

F) D) and E)
G) None of the above

Correct Answer

verifed

verified

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated expected (mean) time for activity E? A) 91 days B) 99 days C) 100 days D) 101 days E) 115 days What is the estimated expected (mean) time for activity E?


A) 91 days
B) 99 days
C) 100 days
D) 101 days
E) 115 days

F) A) and E)
G) D) and E)

Correct Answer

verifed

verified