Filters
Question type

Study Flashcards

Which of the following are advantages of PERT? (I) It is visual. (II) It is automatically updated. (III) Activities that need to be watched closely can be identified.


A) I and II
B) II and III
C) III only
D) I and III
E) I, II, and III

F) A) and B)
G) All of the above

Correct Answer

verifed

verified

What is the probability that this project will be completed within 130 days?


A) .8413
B) .90
C) .9544
D) .9772
E) .9987

F) A) and D)
G) A) and C)

Correct Answer

verifed

verified

A project has the activities and activity times (days) listed below.Determine the probability that the project will require more than 15 days from start to finish.

Correct Answer

verifed

verified

blured image blured image The probability of this proj...

View Answer

The project management strategy of injecting additional resources in order to reduce the length of the project is called:


A) expediting
B) rushing
C) panicking
D) crashing
E) loading

F) All of the above
G) A) and D)

Correct Answer

verifed

verified

Once a project is approved and underway, project managers are only responsible for effectively managing time and costs which, if done well, will assure project completion on time and on budget.

A) True
B) False

Correct Answer

verifed

verified

Gantt charts are most closely associated with


A) JIT
B) PERT
C) MRP
D) MRPII
E) Six Sigma

F) B) and C)
G) A) and E)

Correct Answer

verifed

verified

Using the information given in the following table: (A) Identify the critical path. (B) Determine expected project duration.

Correct Answer

verifed

verified

blured image (A) The critical pa...

View Answer

What is the probability that the critical path for this project will be completed within 75 weeks? 80 weeks? 85 weeks? 90 weeks?

Correct Answer

verifed

verified

.5; .8413;...

View Answer

In PERT, the expected project duration will never exceed the expected duration of the critical path.

A) True
B) False

Correct Answer

verifed

verified

The network diagram describes sequential relationships among major activities on a project.

A) True
B) False

Correct Answer

verifed

verified

What is the probability that this project will be completed within 205 days?


A) 0.6826
B) 0.8413
C) 0.9544
D) 0.9772
E) 0.9987

F) None of the above
G) B) and C)

Correct Answer

verifed

verified

Activity E has an optimistic time of 9 days, a most likely time of 12 days, and a pessimistic time of 15 days.Estimate its expected time and standard deviation.

Correct Answer

verifed

verified

The probability of occurrence of risk events is lower near the beginning of a project and higher near the end of the project since very few activities remain.

A) True
B) False

Correct Answer

verifed

verified

Once a project is underway, the project manager usually is not responsible for effectively managing:


A) the people
B) costs
C) resources
D) time
E) project priority

F) B) and D)
G) None of the above

Correct Answer

verifed

verified

Determine the amount of slack in each of a project's activities (presented below), and identify those that are on the critical path.

Correct Answer

verifed

verified

blured image blured image The crit...

View Answer

What is the probability that the critical path for this project will be completed within 52 weeks?


A) 0.1554
B) 0.3108
C) 0.3466
D) 0.6554
E) 0.8277

F) A) and B)
G) B) and D)

Correct Answer

verifed

verified

What is the probability that this project will take more than 10 weeks to complete if the activity means and standard deviations are as shown below:

Correct Answer

verifed

verified

blured image blured image Prob(duration exce...

View Answer

A Gantt chart is built using established precedence relationships.

A) True
B) False

Correct Answer

verifed

verified

Some organizations use a matrix organization to integrate the activities of specialists within a functional framework.

A) True
B) False

Correct Answer

verifed

verified

A hierarchical listing of what must be done in a project is called:


A) work breakdown structure (WBS)
B) PERT
C) planning matrix
D) crashing
E) critical path

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

Showing 101 - 120 of 137

Related Exams

Show Answer