What are the estimated expected (mean) times (in weeks) for activities A-H?

Correct Answer

verifed

verified

15; 20; 10...

View Answer

Activity 7-8 is directly preceded by two activities-activity 5-7 and activity 6-7.Activity 5-7 has an expected time of five and an ES time of six.Activity 6-7 has an expected time of seven and an ES time of seven.Activity 7-8 has an expected time of 10.The ES for activity 7-8 is:


A) 11
B) 14
C) 21
D) 24
E) 25

F) None of the above
G) A) and E)

Correct Answer

verifed

verified

In crashing this project, which activity should be the first to be reduced?

Correct Answer

verifed

verified

The project computing algorithm requires both a forward and backward pass.

A) True
B) False

Correct Answer

verifed

verified

The main function of dummy activities is to clarify relationships in network diagrams.

A) True
B) False

Correct Answer

verifed

verified

What is the estimated expected (mean) time for activity D?


A) 32 days
B) 41 days
C) 44 days
D) 42 days
E) 40 days

F) A) and B)
G) D) and E)

Correct Answer

verifed

verified

A PERT/CPM activity has an optimistic time estimate of three days, a most likely time estimate of eight days, and a pessimistic time estimate of 10 days.The expected time (in days) of this activity is:


A) 7.0
B) 7.5
C) 8.0
D) 8.5
E) 10.0

F) D) and E)
G) B) and C)

Correct Answer

verifed

verified

What is the total cost of reducing the project to 18 weeks?

Correct Answer

verifed

verified

Total cost...

View Answer

In the probabilistic approach to project network analysis, the time estimate annotated "tm" for any activity is the:


A) mean time
B) median time
C) most likely time
D) mode time
E) marginal time

F) A) and B)
G) B) and D)

Correct Answer

verifed

verified

Which of the following are limitations of PERT? (I) Time estimates may include a fudge factor. (II) Important activities may be overlooked. (III) It is an after-the-fact analysis.


A) I and II
B) I, II, and III
C) I and III
D) II and III
E) I only

F) A) and C)
G) B) and E)

Correct Answer

verifed

verified

A sequence of activities that leads from the starting node to the finishing node is called a _______.


A) Path
B) Sequel
C) Trail
D) Critical sequence
E) Time line

F) D) and E)
G) A) and B)

Correct Answer

verifed

verified

Activity D has an optimistic time of 3 days, a pessimistic time of 9 days, and a most likely time of 4 days.Determine its expected time and variance.

Correct Answer

verifed

verified

te = (to + 4tm + tp)/6 =...

View Answer

Which of the following is not a limitation of PERT and similar project-scheduling techniques?


A) They force the manager to organize and quantify information.
B) One or more important activities may be omitted from the network.
C) Precedence relationships may not all be correct as shown.
D) Time estimates may contain a "fudge factor."
E) The use of a computer is essential for large projects.

F) None of the above
G) C) and D)

Correct Answer

verifed

verified

The earliest finish time for an activity is equal to the latest finish time minus the activity slack.

A) True
B) False

Correct Answer

verifed

verified

In project network analysis, "slack" refers to the difference between:


A) observed and predicted times
B) optimistic and pessimistic times
C) mean and modal times
D) finish and start times
E) latest and earliest times

F) C) and D)
G) A) and B)

Correct Answer

verifed

verified

Which of the following is determined as a direct result of computing the earliest starting and finishing times for the activities of a project network?


A) expected project duration
B) activity slack time
C) which activities are on the critical path
D) variance in project duration
E) maximum project duration

F) B) and E)
G) A) and E)

Correct Answer

verifed

verified

Which of the following lead to simulation being a useful tool with uncertain activity times.


A) paths that aren't independent
B) activity times that aren't deterministic
C) activity times that can't be crashed
D) non-critical paths that have no variability
E) critical paths with activities with deterministic time estimates

F) B) and D)
G) C) and D)