Filters
Question type

Study Flashcards

The contribution margin per unit is equal to the:


A) sales price per unit minus the total costs per unit.
B) variable cost per unit minus the fixed cost per unit.
C) sales price per unit minus the variable cost per unit.
D) pre-tax profit per unit.
E) aftertax profit per unit.

F) A) and E)
G) A) and D)

Correct Answer

verifed

verified

Scenario analysis is best suited to accomplishing which one of the following when analyzing a project?


A) determining how fixed costs affect NPV
B) estimating the residual value of fixed assets
C) identifying the potential range of reasonable outcomes
D) determining the minimal level of sales required to break-even on an accounting basis
E) determining the minimal level of sales required to break-even on a financial basis

F) All of the above
G) A) and B)

Correct Answer

verifed

verified

Miller Mfg.is analyzing a proposed project.The company expects to sell 8,000 units,plus or minus 2 percent.The expected variable cost per unit is $11 and the expected fixed costs are $287,000.The fixed and variable cost estimates are considered accurate within a plus or minus 5 percent range.The depreciation expense is $68,000.The tax rate is 32 percent.The sales price is estimated at $64 a unit,give or take 3 percent.What is the net income under the worst case scenario?


A) $8,578
B) $18,228
C) $15,846
D) $20,704
E) $24,696

F) B) and E)
G) None of the above

Correct Answer

verifed

verified

Cool Shades,Inc.(CSI) manufactures biotech sunglasses.The variable materials cost is $1.69 per unit,and the variable labor cost is $3.04 per unit.Suppose the firm incurs fixed costs of $750,000 during a year in which total production is 450,000 units and the selling price is $11.50 per unit.What is the cash break-even point?


A) 76,453 units
B) 88,652 units
C) 110,783 units
D) 128,907 units
E) 140,768 units

F) None of the above
G) B) and E)

Correct Answer

verifed

verified

By definition,which one of the following must equal zero at the accounting break-even point?


A) net present value
B) internal rate of return
C) contribution margin
D) net income
E) operating cash flow

F) C) and E)
G) A) and D)

Correct Answer

verifed

verified

Scenario analysis is defined as the:


A) determination of the initial cash outlay required to implement a project.
B) determination of changes in NPV estimates when what-if questions are posed.
C) isolation of the effect that a single variable has on the NPV of a project.
D) separation of a project's sunk costs from its opportunity costs.
E) analysis of the effects that a project's terminal cash flows has on the project's NPV.

F) B) and D)
G) A) and B)

Correct Answer

verifed

verified

You are considering a project that you believe is quite risky.To reduce any potentially harmful results from accepting this project,you could:


A) lower the degree of operating leverage.
B) lower the contribution margin per unit.
C) increase the initial cash outlay.
D) increase the fixed costs per unit while lowering the contribution margin per unit.
E) lower the operating cash flow of the project.

F) C) and D)
G) A) and B)

Correct Answer

verifed

verified

Steve,the sales manager for TL Products,wants to sponsor a one-week "Customer Appreciation Sale" where the firm offers to sell additional units of a product at the lowest price possible without negatively affecting the firm's profits.Which one of the following represents the price that should be charged for the additional units during this sale?


A) average variable cost
B) average total cost
C) average total revenue
D) marginal revenue
E) marginal cost

F) A) and B)
G) None of the above

Correct Answer

verifed

verified

When the operating cash flow of a project is equal to zero,the project is operating at the:


A) maximum possible level of production.
B) minimum possible level of production.
C) financial break-even point.
D) accounting break-even point.
E) cash break-even point.

F) B) and D)
G) D) and E)

Correct Answer

verifed

verified

At an output level of 50,000 units,you calculate that the degree of operating leverage is 1.8.What will be the percentage change in operating cash flow if the new output level is 54,500 units?


A) 5.00 percent
B) 6.17 percent
C) 16.20 percent
D) 17.43 percent
E) 20.00 percent

F) C) and E)
G) A) and B)

Correct Answer

verifed

verified

Forecasting risk is defined as the possibility that:


A) some proposed projects will be rejected.
B) some proposed projects will be temporarily delayed.
C) incorrect decisions will be made due to erroneous cash flow projections.
D) some projects will be mutually exclusive.
E) tax rates could change over the life of a project.

F) B) and E)
G) A) and B)

Correct Answer

verifed

verified

Brubaker & Goss has received requests for capital investment funds for next year from each of its five divisions.All requests represent positive net present value projects.All projects are independent.Senior management has decided to allocate the available funds based on the profitability index of each project since the company has insufficient funds to fulfill all of the requests.Management is following a practice known as:


A) scenario analysis.
B) sensitivity analysis.
C) leveraging.
D) hard rationing.
E) soft rationing.

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

A project has a payback period that exactly equals the project's life.The project is operating at:


A) its maximum capacity.
B) the financial break-even point.
C) the cash break-even point.
D) the accounting break-even point.
E) a zero level of output.

F) B) and E)
G) B) and C)

Correct Answer

verifed

verified

Consider a 6-year project with the following information: initial fixed asset investment = $460,000; straight-line depreciation to zero over the 6-year life; zero salvage value; price = $34; variable costs = $19; fixed costs = $188,600; quantity sold = 90,528 units; tax rate = 32 percent.What is the sensitivity of OCF to changes in quantity sold?


A) $10.20 per unit
B) $11.16 per unit
C) $11.38 per unit
D) $12.33 per unit
E) $12.54 per unit

F) A) and E)
G) A) and B)

Correct Answer

verifed

verified

Mountain Gear can manufacture mountain climbing shoes for $15.25 per pair in variable raw material costs and $18.46 per paid in variable labor costs.The shoes sell for $135 per pair.Last year,production was 170,000 pairs and fixed costs were $830,000.What is the minimum acceptable total revenue the company should accept for a one-time order for an extra 10,000 pairs?


A) $149,500
B) $287,600
C) $337,100
D) $380,211
E) $1,164,100

F) A) and E)
G) D) and E)

Correct Answer

verifed

verified

Which one of the following types of analysis is the most complex to conduct?


A) scenario
B) break-even
C) sensitivity
D) degree of operating leverage
E) simulation

F) C) and E)
G) All of the above

Correct Answer

verifed

verified

Wexford Industrial Supply is considering a new project with estimated depreciation of $26,000,fixed costs of $79,000,and total sales of $187,000.The variable costs per unit are estimated at $11.80.What is the accounting break-even level of production?


A) 4,871 units
B) 5,333 units
C) 5,415 units
D) 6,949 units
E) 7,248 units

F) D) and E)
G) A) and C)

Correct Answer

verifed

verified

When you assign the lowest anticipated sales price and the highest anticipated costs to a project,you are analyzing the project under the condition known as:


A) best case sensitivity analysis.
B) worst case sensitivity analysis.
C) best case scenario analysis.
D) worst case scenario analysis.
E) base case scenario analysis.

F) C) and D)
G) B) and D)

Correct Answer

verifed

verified

Theresa is analyzing a project that currently has a projected NPV of zero.Which of the following changes that she is considering will help that project produce a positive NPV instead? Consider each change independently. I.increase the quantity sold II.decrease the fixed leasing cost for equipment III.decrease the labor hours needed to produce one unit IV.increase the sales price


A) I and II only
B) I and IV only
C) II, III, and IV only
D) I, II, and IV only
E) I, II, III, and IV

F) B) and E)
G) A) and B)

Correct Answer

verifed

verified

We are evaluating a project that costs $854,000,has a 15-year life,and has no salvage value.Assume that depreciation is straight-line to zero over the life of the project.Sales are projected at 154,000 units per year.Price per unit is $41,variable cost per unit is $20,and fixed costs are $865,102 per year.The tax rate is 33 percent,and we require a 14 percent return on this project.Suppose the projections given for price,quantity,variable costs,and fixed costs are all accurate to within ±14 percent.What is the worst-case NPV?


A) $984,613
B) $1,267,008
C) $1,489,511
D) $1,782,409
E) $1,993,870

F) A) and D)
G) A) and E)

Correct Answer

verifed

verified

Showing 21 - 40 of 106

Related Exams

Show Answer