Filters
Question type

Study Flashcards

An analysis which combines scenario analysis with sensitivity analysis is called _____ analysis.


A) forecasting
B) scenario
C) sensitivity
D) simulation
E) break-even

F) B) and D)
G) A) and B)

Correct Answer

verifed

verified

What is the benefit of scenario analysis if it does not produce an accept or reject decision for a proposed project?

Correct Answer

verifed

verified

Scenario analysis provides management wi...

View Answer

A project has a contribution margin of $5, projected fixed costs of $10,000, a projected variable cost per unit of $12, and a projected present value break-even point of 6,000 units.What is the operating cash flow at this level of output?


A) $2,000
B) $10,000
C) $20,000
D) $30,000
E) $120,000

F) None of the above
G) B) and C)

Correct Answer

verifed

verified

Wilson's Antiques is considering a project that has an initial cost today of $10,000.The project has a two-year life with cash inflows of $6,500 a year.Should Wilson's decide to wait one year to commence this project, the initial cost will increase by 5% and the cash inflows will increase to $7,500 a year.What is the value of the option to wait if the applicable discount rate is 10%?


A) $1,006.76
B) $1,235.54
C) $1,509.28
D) $1,606.76
E) $1,735.54

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

Fixed costs: I.are variable over long periods of time. II.must be paid even if production is halted. III.are generally affected by the amount of fixed assets owned by a firm. IV.per unit remain constant over a given range of production output.


A) I and III only
B) II and IV only
C) I, II, and III only
D) I, II, and IV only
E) I, II, III, and IV

F) All of the above
G) A) and D)

Correct Answer

verifed

verified

Simulation analysis is based on assigning a _____ and analyzing the results.


A) narrow range of values to a single variable
B) narrow range of values to multiple variables simultaneously
C) wide range of values to a single variable
D) wide range of values to multiple variables simultaneously
E) single value to each of the variables

F) B) and C)
G) D) and E)

Correct Answer

verifed

verified

Which of the following statements are correct concerning the present value break-even point of a project? I.The present value of the cash inflows equals the amount of the initial investment. II.The payback period of the project is equal to the life of the project. III.The operating cash flow is at a level that produces a net present value of zero. IV.The project never pays back on a discounted basis.


A) I and II only
B) I and III only
C) II and IV only
D) III and IV only
E) I, III, and IV only

F) A) and E)
G) D) and E)

Correct Answer

verifed

verified

Consider the following statement by a project analyst: "I analyzed my project using scenarios for the base case, best case, and worst case.I computed break-evens and degrees of operating leverage.I did sensitivity analysis and simulation analysis.I computed NPV, IRR, payback, AAR, and PI.In the end, I have over a hundred different estimates and am more confused than ever.I would have been better off just sticking with my first estimate and going by my gut reaction." Critique this statement.

Correct Answer

verifed

verified

The goal of evaluating an NPV estimate o...

View Answer

Discuss two shortcomings in the standard decision tree analysis that a financial manager should be cognizant of?

Correct Answer

verifed

verified

First, there is differential risk at var...

View Answer

All else constant, as the variable cost per unit increases, the:


A) contribution margin decreases.
B) sensitivity to fixed costs decreases.
C) degree of operating leverage decreases.
D) operating cash flow increases.
E) net profit increases.

F) A) and E)
G) B) and E)

Correct Answer

verifed

verified

Ralph and Emma's is considering a project with total sales of $17,500, total variable costs of $9,800, total fixed costs of $3,500, and estimated production of 400 units.The depreciation expense is $2,400 a year.What is the contribution margin per unit?


A) $4.50
B) $10.50
C) $14.14
D) $19.09
E) $19.25

F) A) and B)
G) None of the above

Correct Answer

verifed

verified

Sensitivity analysis is a method which allows for evaluation of the NPV given a series of changes to the underlying assumptions.Discuss why and how scenario analysis is used in addition to sensitivity analysis.

Correct Answer

verifed

verified

Sensitivity analysis:
measures result of...

View Answer

As the degree of sensitivity of a project to a single variable rises, the:


A) lower the forecasting risk of the project.
B) smaller the range of possible outcomes given a pre-defined range of values for the input.
C) more attention management should place on accurately forecasting the future value of that variable.
D) lower the maximum potential value of the project.
E) lower the maximum potential loss of the project.

F) C) and D)
G) A) and B)

Correct Answer

verifed

verified

Variable costs:


A) change as the quantity of output changes.
B) are zero when production is zero.
C) are exemplified by direct labor and raw materials.
D) All of the above.
E) None of the above.

F) All of the above
G) A) and D)

Correct Answer

verifed

verified

All else equal, the contribution margin must increase as:


A) both the sales price and variable cost per unit increase.
B) the fixed cost per unit declines.
C) the variable cost per unit declines.
D) sales price per unit declines.
E) the sales price minus the fixed cost per unit increases.

F) C) and D)
G) All of the above

Correct Answer

verifed

verified

Sensitivity analysis provides information on:


A) whether the NPV should be trusted and may provide a false sense of security if all NPVs are positive.
B) the need for additional information as it tests each variable in isolation.
C) the degree of difficulty in changing multiple variables together.
D) Both A and B.
E) Both A and C.

F) All of the above
G) A) and C)

Correct Answer

verifed

verified

A project has earnings before interest and taxes of $5,750, fixed costs of $50,000, a selling price of $13 a unit, and a sales quantity of 11,500 units.Depreciation is $7,500. What is the variable cost per unit?


A) $6.75
B) $7.00
C) $7.25
D) $7.50
E) $7.75

F) B) and C)
G) All of the above

Correct Answer

verifed

verified

Which one of the following is most likely a variable cost?


A) office rent
B) property taxes
C) property insurance
D) direct labor costs
E) management salaries

F) A) and B)
G) None of the above

Correct Answer

verifed

verified

Fixed costs:


A) change as the quantity of output produced changes.
B) are constant over the short-run regardless of the quantity of output produced.
C) reflect the change in a variable when one more unit of output is produced.
D) are subtracted from sales to compute the contribution margin.
E) can be ignored in scenario analysis since they are constant over the life of a project.

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

The market value of an investment project should be viewed as the sum of the standard NPV and the value of managerial options.Explain three different real or managerial options that management may have, what they are, and how they would influence market value.

Correct Answer

verifed

verified

There are three commonly used real optio...

View Answer

Showing 21 - 40 of 90

Related Exams

Show Answer